This PPP project developed within the “infrastructural corridor 5” along the High Speed Torino-Trieste railway line (Milan-Verona section), aims at the implementation of a direct link among Brescia, Bergamo and Milan, in the most industrialized area of the country.

Project Data

Country: Italy
Location within country: Lombardia
Name of Client: BRE.BE.MI. S.p.A

Services
  • Preliminary design
  • Final design
  • Environmental Impact Assessment
  • Environmental Monitoring
  • Tolling Plaza localization strategy
  • Resettlement plan
  • Land Expropriation
Back to Projects Archive
image009

Project Introduction
This PPP project developed within the “infrastructural corridor 5” along the High Speed Torino-Trieste railway line (Milan-Verona section), aims at the implementation of a direct link among Brescia, Bergamo and Milan, in the most industrialized area of the country.  The BreBeMi is a three lanes highway, in addition to the emergency lane, for a total length of 62,1 km, divided into:

•embankments: 37,9 km
•cuts: 19,2 km
•viaducts: 3,7 km
•tunnels: 1,3 km

In addition to the highway section, the project includes 35 km of urban roads.
The design  impacts an area between the  highway section and  the railway line of about 160 hectares, for which a specific resettlement and restoration plan has  been foreseen.