A14 upgrading of Bologna ring-road

Environment

Supervision of works of about 14 km of A1 highway widening. Upgrading of highway system for Bologna node and ring-road around the city.

Project Data

Country: Italy
Location within country: Emilia Romagna
Name of Client: Autostrade per l’Italia S.p.A
Time frame: 2004 – 2008
Works amount:  about € 115 million

Services
  • Works Supervision
  • Environmental Impact Study
  • Environmental monitoring during construction phase
  • Safety coordination during construction phase
Back to Projects Archive
Tangenziale Bologna - _mg_9670

Project Introduction
Supervision of works of about 14 km of A1 highway widening. Upgrading of highway system for Bologna node and ring-road around the city.
The project includes the construction of a series of works in favour of the territory, including:

  • the new highway “Bologna Fiera” whose works were completed on December 2006, four months ahead of time compared to contract
  • the construction of the new junction on ordinary roads in Crespellano
  • the design and implementation of the Provincial Road Bazzanese
  • changes to existing interchanges on most of the Bologna ring road with the construction of new ramps and roundabouts to improve functionality and increase traffic flow
  • installation of noise barriers, for a total of 9 km in the vicinity of residential areas
  • the construction of the noise mitigation tunnel near S.Donnino